Emergency bridge Copenhagen Airport
In October 2019, we were contacted because our client was looking for a solution to install a temporary pedestrian bridge across an approximately 50 meter wide construction pit, to provide an emergency escape route from Terminal 2 to the platform. The bridge should comply to the Eurocode and should meet the IFD-principles (Industrial, Flexible and Demountable).
In full cooperation with Per Aarsleff A/S we have worked out a two span footbridge with a total length of 52,3 meter and a walkable width of 3 meter.
The bridge was prefabricated in the Netherlands, transported on two trucks to Copenhagen, and installed on September 9 - 2020 within 3 hours.

For the aerial pictures we want to thank our client Per Aarsleff and Luftfotodanmark.
                                Project details
Solution
                Pedestrian bridge
            Type
                JPB-P
            Solution
                Emergency Footbridge
            Total bridge length
                52,3 meter
            Modular field length
                3,05 meter
            Width
                3 meter
            